City of SLO Construction Update - Week of 07/26/10
Look for updates during the week at http://www.slocity.org/publicworks/construction/commuterupdts.asp
Toro Street between Walnut Street & Phillips Lane
Waterline work
Shifting block closures on Toro from Walnut Street to Phillips Lane 8:00 AM – 4:00 PM
Northbound HWY 101 On Ramp closed Monday to Friday 7:00 AM - 3:00 PM
Moderate vehicle delays anticipated
12 Highland Drive
Water line work
Traffic periodically limited to 1 lane with flagging Monday to Friday 8:00 AM – 4:00 PM
Shoulders closed Monday to Friday 8:00 AM – 4:00 PM
Minor vehicle delays anticipated
California Boulevard north of Foothill intersection
Bicycle Path construction
Lane/ bike lane control southbound California Boulevard Monday to Friday 8:00 AM – 4:00 PM
Minor vehicle delays anticipated
Garden Street between Marsh & Higuera
Utility work
One lane of Traffic only Monday 4:00 AM to 12:00 Noon
Marsh Street at Morro
Paving for Fire line installation (Union Bank)
One lane of Traffic only Monday and Tuesday 4:00 AM to 12:00 Noon
Broad Street between Higuera & Marsh
Fire line installation
Lane control around work 7:00 AM to 5:00 PM
Minor vehicle delays anticipated
Foothill Boulevard at Carpenter Street
Fire line installation
Lane control around work 7:00 AM to 5:00 PM
Minor vehicle delays anticipated
700 Block Higuera
Fire line installation
Pedestrian walk diversions/possible lane control 7:00 AM to 5:00 PM
Marsh Street between Carmel & Archer
Fire Line installation
Fire Hydrant installation
Lane closure 4:00 AM to 12:00 Noon
3991 S. Higuera
Bus Shelter installation
Bike lane closure 7:00 AM to 4:00 PM
Minor delays
Augusta Street between Bishop and & San Mateo
Road Closure with detours or lanes closed 7:00 AM to 5:00 PM
North Chorro between Foothill and Boysen
Lane closure with flaggers 7:00 AM to 4:00 PM
Sacramento between Orcutt and Via Estaban
Lane closures with flaggers 7:00 AM to 4:00 PM
South Higuera at Prado
Reclaimed Water Main installation
One lane North bound and one lane South bound closed 7:00 AM to 4:00 PM
Minor Traffic Delays
South Boundary of Cal Poly
3 week installation of overhead and underground utilities starting Monday July 26
Start at Slack and Henderson
Route to Slack and Grand; Slack and Longview; Longview and Hathaway; Hathaway and Carpenter
Finish at Foothill and California
Rolling traffic control – lane closure with flaggers 7:00 AM to 5:00PM
For Caltrans road closure information, visit http://www.dot.ca.gov/dist05/road_information.htm